JES Iteration3 Plan

Plan:

  • Enhancement and Consolidation of Iteration2: start + 3Weeks(01/07/03 -- 04/08/03)
    • Code revision - complete
    • JUnit test in place, but only common area tests in place.
    • Refactoring including jConfig Message/Error Logs. Complete. Has meant generating a common work package for AstroGrid.
    • Building stubs and delegates. Done

  • New Functions in Iteration3: 27/07/03 -- 15/09/03
    • JBL:
      • JES - Get Job List
      • JES - Status Request
      • JES - Submit Job
      • PortalSvr Run Job and associated (PJN understudy)
      • PortalSvr Create Job Page and associated (+PJN +RP)
    • PJN:
      • Understudy to all JES work
      • PortalSvr Job Monitor and associated (JL understudy)
    • RP:
      • PortalSvr Create Job Page and associated

  • Risks:
      • PortalSvr Create Job Page and associated

  • Holidays:
      • JL to be decided (adhoc)
      • PJN to be decided
      • RP 01/08/2003 - 18/08/2003

  • Code freeze by 15/09/03

-- JeffLusted - 04 Aug 2003

Edit | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r1 | More topic actions
 
AstroGrid Service Click here for the
AstroGrid Service Web
This is the AstroGrid
Development Wiki
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback