MySpace Iteration3 Plan and Forecast

Plan:

  • Enhancement and Consolidation of Iteration2: start + 3Weeks(01/07/03 -- 25/07/03)
    • Code revise and UML reflect current code in place: done
    • Test environment set up:Tomcat/Axis,TogetherSoft(optional): ACD will try to use grendel12 to perform ServerSide? Test.
    • JUnit test in place: Week2: almost done
    • Web Services Up and Running: done
    • External Interface in place: done
    • Refactoring including jConfig Message/Error Logs -- Week2+Week3: still need to be completed
    • Bug Fixing and Unit Testing: All through Consolidation Period. ACD and CLQ: on going
    • Study Registry and find out similarity between Registry and MySpaceRegistry: not nessesary for Iteration 3.
    • get certificate from e-science ACD and CLQ
    • Building stubs and (dummy)MySpaceManager Service stubs and delegates for other WG to access: done

  • New Functions in Iteration3: 04/08/03 -- 15/09/03
    • ACD:
      • Upload/download(including Ftp transferring or http transferring investigation)
      • CreateUser
      • DeleteUser
      • ChangeOwner
      • StructureMySpace
      • Backup Registry file
    • BKM:
      • Integrating Dave's MSExplore and emelfm' look and feel - Before 18th Aug 2003)
      • Adding new functionalities and Authorise(Working with CLQ) - after 5th Sep 2003
    • CLQ:
      • UML plan
      • ServerToServer use case
      • Authorise (Working with Brian)
      • Extend Lease
      • Publish
Time allocation:
    • Holidays:
      • BKM: 18th Aug to 5th Sep
      • ACD: 18th Aug to 29th Aug
    • Booked time for other activities:
      • CLQ: 18th Aug to 29th Aug - prepare All-hands E-Science meeting talk in Nottingham
      • CLQ: 2nd Sep to 4th Sep All-hands E-Science meeting in Nottingham
      • ACD: 11th Aug
      • BKM: basicly being devided between Community and MySpace so half time.
    • Useable Time for Iteration 3 from 4th Aug till 15th Sep(Code freeze)
      • CLQ: 4.5 weeks
      • ACD: 4 weeks
      • BKM: 1.5 weeks
      • TOTAL: 10 weeks

Quality control:

  • Should have Continuous integration testing throughout It3.
  • Should integrate with portal/community asap.
  • Developers check code into CVS /devel at least once everyday.
  • Workgroup leader update UML Model and stable code into CVS /release every week(every Friday)
  • Training: AstroGrid will be setting up a support/training page.
  • Unit test! Write Unit test while coding.
  • Using Ant build while deploying.
  • Communication within team: dayly question/anwser via email/telephone; weekly teleconf(every Monday afternoon); monthly face-to-face meeting.
  • Communication between workgroups!
  • Code freeze by 15/09/03

-- CatherineQin - 01 Aug 2003

Edit | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r3 < r2 < r1 | More topic actions
 
AstroGrid Service Click here for the
AstroGrid Service Web
This is the AstroGrid
Development Wiki
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback