MySpace Iteration3 Plan and Forecast
Plan:
Enhancement and Consolidation of Iteration2: start + 3Weeks(01/07/03 -- 25/07/03)
Code revise and UML reflect current code in place: done
Test environment set up:Tomcat/Axis,TogetherSoft(optional): ACD will try to use grendel12 to perform
ServerSide
?
Test.
JUnit test in place: Week2: almost done
Web Services Up and Running: done
External Interface in place: done
Refactoring including jConfig Message/Error Logs -- Week2+Week3: still need to be completed
Bug Fixing and Unit Testing: All through Consolidation Period. ACD and CLQ: on going
Study Registry and find out similarity between Registry and MySpaceRegistry: not nessesary for Iteration 3.
get certificate from e-science ACD and CLQ
Building stubs and (dummy)MySpaceManager Service stubs and delegates for other WG to access: done
New Functions in Iteration3: 04/08/03 -- 15/09/03
ACD:
Upload/download(including Ftp transferring or http transferring investigation)
CreateUser
DeleteUser
ChangeOwner
StructureMySpace
Backup Registry file
BKM:
Integrating Dave's MSExplore and emelfm' look and feel - Before 18th Aug 2003)
Adding new functionalities and Authorise(Working with CLQ) - after 5th Sep 2003
CLQ:
UML plan
ServerToServer use case
Authorise (Working with Brian)
Extend Lease
Publish
Time allocation:
Holidays:
BKM: 18th Aug to 5th Sep
ACD: 18th Aug to 29th Aug
Booked time for other activities:
CLQ: 18th Aug to 29th Aug - prepare All-hands E-Science meeting talk in Nottingham
CLQ: 2nd Sep to 4th Sep All-hands E-Science meeting in Nottingham
ACD: 11th Aug
BKM: basicly being devided between Community and MySpace so half time.
Useable Time for Iteration 3 from 4th Aug till 15th Sep(Code freeze)
CLQ: 4.5 weeks
ACD: 4 weeks
BKM: 1.5 weeks
TOTAL: 10 weeks
Quality control:
Should have Continuous integration testing throughout It3.
Should integrate with portal/community asap.
Developers check code into CVS /devel at least once everyday.
Workgroup leader update UML Model and stable code into CVS /release every week(every Friday)
Training: AstroGrid will be setting up a support/training page.
Unit test! Write Unit test while coding.
Using Ant build while deploying.
Communication within team: dayly question/anwser via email/telephone; weekly teleconf(every Monday afternoon); monthly face-to-face meeting.
Communication between workgroups!
Code freeze by 15/09/03
--
CatherineQin
- 01 Aug 2003
E
dit
|
A
ttach
|
P
rintable
|
R
aw View
|
Backlinks:
We
b
,
A
l
l Webs
|
H
istory
: r3
<
r2
<
r1
|
M
ore topic actions
Astrogrid
Astrogrid Web
Astrogrid Web Home
Changes
Topic list
Search
Adv Search
TWiki Webs
AG2
Astrogrid
Deploy
Main
PS1
SKUA
SSVO
Sandbox
Schoolgrid
Support
TWiki
UKIDSS
VISTA
Click here for the
AstroGrid Service Web
This is the AstroGrid
Development Wiki
Copyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki?
Send feedback