Working Plan
A very very rough draft framework...
Staff & Organisation
Working Team
Implementers:
Reporting to:
Astronomy and Technical Consultants:
Collaborations
Interfacing with other working groups:
- Project Management - Peter Quinn, with Markus helping on technical side
- Science Work Area - Piero B / Nick Walton - short of people.
- Interoperability - Francoise / CDS - federating archives
- Infrastructure - Andy Lawrence - AstroGrid overlap
Interfaces / Resources
- Image formats (CDS? ESO?)
- SExtractor
- Result sets suitable for Aladdin - VOTable?
- CDS - interfacing - static tables of catalogues
- ESO - Providing calibrating data, images (pixel data) & catalogues
Louise de Costa - he's been doing some image proccessing already on the South Deep Field, so can provide/help with making parameter templates for SExtractor
Testing
Lots - this is to be used for Real Science. As such it must be reliable or people will be put off right at the beginning.
Plan
Work breakdown
Requirememts & Interfaces agreed
- Image formats
- Output (VOTable XML/FITS)
- Confirm SOAP documents do what we expect.
Design:
- Demo AstroGrid Protocol defined & agreed (done)
- Component interfaces agreed
Document
- Test cases agreed.
- Code documentation up to package level should be JavaDoc .
- TogetherJ used for diagramming.
Implementation:
Test, test, test:
- Against hand-run SExtractor
- Assemble test data & confirmed correct results (--> version control).
NB - important that this initial service is reliable, otherwise users loose faith
Milestones
end Sep - System-level setup completed:
- Apache/Axis servers installed & configured at development sites
- Version control available
(Initial) Design & Research completed
Oct/Nov - develop & unit test components.
Dec - Integration & System testing.
Risks
| Risk |
Effect |
Likelihood |
Action |
| Dodgy Requirements |
|
|
Get in there and make 'em |
| Interfaces with AVO |
|
Not many of them |
Make sure they're clear |
| Other tasks |
Divertion |
Likely |
Prioritise. Agree & Assign proportion of time. |
| Geographically separated workforce |
Lost time working on out-of-date specs, Lost time on travelling to meetings, lost time on no casual questions |
Certain |
Loosely couple tasks. Max use of forums/emails/phones. Web version control. |
--
MartinHill - 28 Aug 2002