AG2 SCHEDULE
Proposal from Andy Lawrence for AGLI approval, March 8th 2004.
The schedule should evolve from the aims and constraints, so first
some general points.
(1) GENERAL POINTS
1.1 We have already agreed the general approach at Jan meeting :
- all institutions have re-affirmed their involvement
- SSVO merge with AG2
- resource allocations deferred until after design study
- design study already underway and also Forum topic : Tony to report
1.2 Personnel management :
- agreed to extend contracts for PM, PS, TL
- has been verbally agreed with PPARC, formal arrangements underway.
- other AG1 staff : announce late enough not to encourage early departures
- but early enough to give people a chance to find other jobs
- some staff contracts end October : need warning by August
- informal preliminary staff ranking exists
- proposal for additional effort from Pye : project assistance
1.3 PPARC expectations
- preliminary plans described to GSC in February
- committed ourselves to showing them Project Plan in "late summer"
- they will want to see clear evidence of organised plan of work
- but won't care about resource distribution : up to us.
1.4 Project Psychology
- PPARC thinking of us "continued AstroGrid"
- but we should think of distinct projects
- AstroGrid-1 MUST DELIVER : AG2 not an excuse to delay
- descope AG1 as necessary to deliver product
- want clear set of additional goals for AG2
- also want clear fresh-start planning without disturbing AG1 work.
(2) DOCS TO PRODUCE
2.1 Design Study
- informal documents for internal AG debate
- three parts :
(a) Technical scope (TL leading)
(b) Science scope (NAW leading)
(c) AG1 stock taking (AL to lead)
- needs to be done pretty soon so we can iterate
2.2 Project Plan
- this is the bit that needs to re-assure PPARC
- so needs to be done by summer
- but can also be a document we circulate publicly
- parts needed are :
(a) AG2 vision document : including top-level goals
(b) Architecture overview
(c) Management Plan : deliverables, milestones, risk table
staffing plan, hardware plan
budget
2.3 Design Reference Architecture
- arch overview in summer project plan
- real architecture evolves continuously of course
- but we commit to having something in place that developers can seriously work against
- done by October ?
(3) TIMETABLE
Later dates need revising when we know GSC date.
Jan 31 : agree membership, initial approach
March 8 : AGLI telecon
: agree doc plan and schedule
March 28 : first draft Design Study
April 2 : debate at NAM
April 15 : final Design Study
: outline Project Plan
Apr 21 : AGLI telecon
review of AG2 development
May 15 : draft Project Plan
June 1 : AGLI telecon
review Project Plan
June 7 : AGLI telecon
sign-off final project plan
sign-off revised milestone plan
send to PPARC
mid-June : GSC review project plan ?? + feedback
July 1 : revised Project Plan
July 15 : final AGLI review
Aug 1 : announce staffing plan to staff
Oct 1 : Design Reference Architecture
--
AndyLawrence - 08 Mar 2004