AstroGrid Project

AstroGrid2 Project Development : schedule update

June 29th 2004

Andy Lawrence
AstroGrid Project Leader
University of Edinburgh

E-mail: al@roe.ac.uk

Here is the schedule we set ourselves, and a summary of how we are progressing. This was roughly in place in Januray, but "Original date" means the formally agreed schedule at the April telecon, and "Revised Date" the schedule agreed at the last telecon (June 7th).

Item Orig.Date Rev. Date Completion Date Status Note
agree membership, initial approach Jan 31 ---- Jan 31 DONE  
agree doc plan and schedule March 8 ----- March 8 DONE  
discussion at NAM April 1 ---- April 1 DONE  
Telecon progress review April 8 ---- April 8 DONE  
Consortium meeting April 8 ---- April 26 AGLI meeting held  
draft design study April 8 ---- June 7 DONE Note (i)
outline project plan April 8 ---- June 7 key principles laid out Note (ii)
final design study May 15 July 7 June 29 essentially complete Note (i)
draft Project Plan May 15 July 7 June 29 part complete Note (ii)
review Project Plan June 1 ---- June 7 key principles agreed  
sign-off project plan
and milestones
June 7 TBD ----   Note (ii)
send plan to PPARC June 7 TBD ---- Unknown delay Note (iii)
receive GSC feedback mid-June TBD ---- Unknown delay Note (iii)
revised Project Plan July 1 TBD ---- Unknown delay Note (iii)
announce staffing plan to staff July 1 ---- ---- On schedule (just) Note (iv)
Design Reference Architecture Oct 1 ---- ---- On schedule  

Note (i) : Design Study. The first cut at the design study (Technical Scope doc) was well ahead of schedule. The Science Scope doc appeared just before the last telecon. The Vision Doc is the opening part of the new Project Plan. Fairly detailed architecture notes from Guy have now also appeared. Detailed design will continue, but the study required to make a rational project plan is now essentialy complete.

Note (ii) : Project Plan. This is is some way behind where we wanted, but is at last coming into view. At the last telecon we agreed the key principles of the project plan and a revised dates for a "good draft". The key components are the work plan and staffing plan, which follow on from the results of the design study. These are drafted but require AGLI approval. Deliverables, milestones, and risk plan still need to be done. Given the uncertainty of the PPARC context (see below) the slipping of the overall Project Plan isn't too crucial, but we decided last time that we must keep the staffing plan on schedule, which requires an agreed work plan.

Note (iii) : PPARC context. As noted at the last telecon, we are still waiting to hear what hoops we have to jump through for which committee. (We will probably be reporting to a re-formed AstroGrid oversight committee and occasionally to an overall PPARC computing committee). Agreeing the staffing plan, and beginning to negotiate new grants, is probably more important just now for Swindon office, just as it is for us.

Note (iv) : Staffing Plan. Confidential rankings for existing staff are fairly well agreed. Proposals for new staff have been received and will be reviewed at this telecon. The main uncertainty remains the level of EC funding. A work plan is drafted which will help inform final decisions. The target for today should be a preliminary agreement on a complete staffing plan, and firm agreement on some immediate short term actions.